Tracking production output and work in process

Track input, good completions, scrap and the remaining balance by operation to explain unfinished work.

Author
Seung-joo Park
Reviewer
Seung-joo Park
Last updated

The companies, items and codes in this article are fictional examples for teaching.

How we write and review

Applying the rule

All 20 assemblies were posted as finished although only 16 passed final inspection.

The correction left 16 finished and restored 4 awaiting inspection to WIP.

A fictional example from the companion lesson

Situation
Fictional example · The Hanbit Stationery production team skipped assembly and packed cut parts directly. Finished counts rose, but unassembled parts piled up between steps and the books stopped matching the floor. (Quantities are made-up teaching numbers.)
Result
Skipping steps makes WIP vanish from the books and finished goods look higher than they are, so cost and stock go wrong.

Decision table

Identify the applicable condition and use the action in the right column.
BranchConditionAction
First caseWaitingRetain WIP
Second caseFinal acceptanceReceive finished goods

Frequently asked questions

Where does a unit under rework belong?

Until acceptance criteria are met, track rework quantities at their operation within WIP.

How should the example in this article be handled?

The correction left 16 finished and restored 4 awaiting inspection to WIP.

If we skip a step, won't finished goods rise faster?

Work-in-progress is unfinished goods between steps. Input, output and WIP must add up for the books to match the floor.