Work in process disappeared between operations

An intermediate completion was booked as final output, removing units waiting for the next operation from WIP.

Author
Seung-joo Park
Reviewer
Seung-joo Park
Last updated

This case is a made-up story

It is not about a real company or customer. The companies, items, codes and numbers are values invented to explain the idea, not real statistics or results.

How we write and review

Where the discrepancy began

Matching intermediate completions to final inspection exposed finished receipts without corresponding acceptances.

A fictional worked example

Situation
Fictional example · All 20 assemblies were posted as finished although only 16 passed final inspection.
Result
The correction left 16 finished and restored 4 awaiting inspection to WIP.

A check to prevent recurrence

Reconcile final operation, inspection acceptance and finished receipts by work order.