Why look at the defect rate, not the defect count?

Calculate the defect rate and passing quantity from inspected and defective pieces, find wrong lines in an inspection report and learn why rates, not counts, are compared.

Author
Seung-joo Park
Reviewer
Seung-joo Park
Last updated

The company, items and quantities in this lesson are all fictional and for education only.

How we write and review lessons

WHY — why does it matter?

Step 1 of 6

Is the line with the most defects the worst one?

Situation
Hanbit Stationery’s quality lead picked the line with the most defects this month for improvement. That line, however, had inspected ten times more than the others. (Quantities are made-up teaching numbers.)
Problem
The defect rate is the share of defective pieces among all inspected. It lets lines or lots with different quantities be compared on the same basis.
If it goes wrong
Comparing counts makes the line that produces the most always look worse, and the line with the real problem is missed.