Why is more material put in than finished goods come out?

Calculate yield and loss from input and output quantities, find wrong lines in a production report, and learn why loss must be recorded.

Author
Seung-joo Park
Reviewer
Seung-joo Park
Last updated

The company, items and quantities in this lesson are all fictional and for education only.

How we write and review lessons

WHY — why does it matter?

Step 1 of 6

If 500 goes in, why doesn't 500 come out?

Situation
A Hanbit Stationery factory put 500 units of raw material in, but only 460 finished goods came out. The report gave no reason for the missing 40, so the manager suspected theft. (Quantities are made-up teaching numbers.)
Problem
Yield is finished output as a share of input; loss is the quantity lost during the process. Recording both lets you find the cause and improve.
If it goes wrong
Without loss records the waste is invisible, and the same loss repeats every run.