Setting safety stock

Safety stock buffers demand variability or delays during replenishment. Size it using observed demand and supply uncertainty.

Author
Seung-joo Park
Reviewer
Seung-joo Park
Last updated

The companies, items and codes in this article are fictional examples for teaching.

How we write and review

Applying the rule

Assume demand of 4 per day, lead time of 5 days and safety stock of 6.

The simple reorder point is 4 × 5 + 6 = 26, including the 6-unit buffer.

A fictional example from the companion lesson

Situation
Fictional example · Hanbit Stationery’s pen supplier takes 5 days from order to receipt, yet the clerk ordered only once stock hit zero. One week, orders piled up and customers were told of a 3-day stock-out. (Quantities are made-up teaching numbers.)
Result
Ordering at zero without a rule leaves nothing to sell during lead time, while an oversized safety stock piles up holding cost.

Decision table

Identify the applicable condition and use the action in the right column.
BranchConditionAction
First caseStable demandReview observed variation
Second caseUnstable supplyReassess delay exposure

Frequently asked questions

Should every item have the same buffer?

Substitutability, demand variability and actual lead times differ, so equal buffers offer different protection.

How should the example in this article be handled?

The simple reorder point is 4 × 5 + 6 = 26, including the 6-unit buffer.

Why not wait until stock runs out before ordering?

The reorder point is the level at which you order now. Set it as the quantity sold during lead time plus safety stock, and stock-outs do not occur before the delivery arrives.