Linking production plans to material requirements

Multiply planned output by the effective BOM quantities, then net usable stock and receipts confirmed by the need date.

Author
Seung-joo Park
Reviewer
Seung-joo Park
Last updated

The companies, items and codes in this article are fictional examples for teaching.

How we write and review

Applying the rule

Ten products need 3 parts each, with 8 available and 7 due before production.

Without other demand, net requirement is 30 − 8 − 7 = 15.

A fictional example from the companion lesson

Situation
Fictional example · Hanbit Furniture received an order for 50 desks. The plant clerk once ordered parts by gut feeling and the line stopped mid-run for lack of legs. (Parts and quantities are made-up teaching data.)
Result
Buying by gut feeling leaves some parts short, stopping production, and others in surplus, tying up stock and money.

Decision table

Identify the applicable condition and use the action in the right column.
BranchConditionAction
First caseAvailable in timeNet against need
Second caseLate receiptRetain shortage

Frequently asked questions

Should every scheduled receipt reduce requirements?

Net only confirmed supply usable by the need date and keep late receipts in their actual time bucket.

How should the example in this article be handled?

Without other demand, net requirement is 30 − 8 − 7 = 15.

The desks are ordered, but parts run short.

When the parts and quantities for one product are fixed in a bill of materials, multiplying by the number to make gives each part’s need, and comparing with stock tells what to buy.