Calculating supplier on-time delivery

Divide lines fulfilled by their agreed date by lines due in the period. State how partial deliveries and rescheduling are treated.

Author
Seung-joo Park
Reviewer
Seung-joo Park
Last updated

The companies, items and codes in this article are fictional examples for teaching.

How we write and review

Applying the rule

Of 10 lines due, 8 arrived in full by the agreed date.

On a complete-line basis the rate is 80%, including the 2 outstanding lines in the denominator.

A fictional example from the companion lesson

Situation
Fictional example · A Hanbit Stationery buyer believed supplier A always delivered on time. Yet deliveries after the promised date kept piling up, production stopped often, and there was no record to find the cause. (Quantities and dates are made-up teaching data.)
Result
Without delivery records, repeated delays go unnoticed and there is no basis for negotiating with the supplier.

Decision table

Identify the applicable condition and use the action in the right column.
BranchConditionAction
First caseComplete on timeCount on-time line
Second casePartial on timeMark incomplete under full-line rule

Frequently asked questions

What if the supplier revises the due date?

Preserve the original and approved revised dates and use the stated benchmark consistently across periods.

How should the example in this article be handled?

On a complete-line basis the rate is 80%, including the 2 outstanding lines in the denominator.

As long as goods arrive, isn't that enough?

The promised date is the delivery date agreed with the supplier. Recording promised and actual dates side by side separates on-time, late and early receipts and shows supplier reliability.